2015-02-05 - 17069 - Service Request - Analyze ATP dates & stock for two materials #ProductionBreakFix #MMPPSupport

2015-02-05 - 17069 - Service Request - Analyze ATP dates/stock for two materials

Problem Summary


User claiming that ATP stock is not accurate for plant 0210 and provided two materials to analyze.

Admin Info



Purpose
Analyze ATP dates/stock for two materials
Requested by
Babu Lankipalli
Issue Date
02-05-2015
Resolved by
Laxman
Resolved Date
02-08-2015
Document Status
Complete

Detailed Problem Description

(Include Screen Shots if required )

User Beena claiming that ATP is calculation is wrong for plant 0210 and given below two materials to analyze.
10951325
80101941

Solution Analysis and Recommendations

(Include Screen Shots if required)

Analyzed the ATP calculation using above two materials in plant 0210 and realized that APTS is working perfectly. Understand that user wrongly understand the ATP calculation. Detailed analysis is forwarded to user (given below).

Please find below analysis.

  1. For material: 10951325

Total replenishment lead time : 82 days + 7 days GR time (coming to 05/06/2015)
Availability check: Z2 (Check with RLT)

Freely available stock: 72
Requirement qty and date: 36 EA & 03/30/2015
36 EA & 05/28/2015

So requirement within RLT is 36 EA (03/30/2015). Balance qty within RLT is 36 (72-36) nothing but ATP qty.


  1. For material: 80101941

Total replenishment lead time : 90 days + 7 days GR time (coming to 05/14/2015)
Availability check: Z2 (Check with RLT)

Freely available stock: 320
Requirement qty and date: 72 EA & 02/15/2015
120 EA & 03/30/2015
120 EA & 05/28/2015

So requirement within RLT is 72+120 EA (02/15/2015 & 03/30/2015). Balance qty within RLT is 128 (320-192) nothing but ATP qty.

Resolution


After sending the analysis user understood the correct calculation of ATP.